206619

GLAND, CABLE: E1FW, 20S/M20 EXD, GLAND FOR CU/XLPE/PVC/SWA/PVC 1KV CABLE, FOR ZONE II IIC T3 (MIN), -60...+130°C, INNER DIA 6.1 – 11.7 / OUTER DIA 9.5 – 15.9 MM, C/W NYLON WASHER [IP66 MIN.], BRASS EARTH TAG, BRASS LOCK NUT AND STAINLSS STEEL SERRATED WAS
FPAL 1.9.9.0 · Basic Consumables · Nature Consumable

Категория материала

Electrical Equipment & Materials Transformers / Switchgear Spare
FPAL1.9.9.0 из SAP

Stock & pipeline (latest SRR snapshot)

Total balance
152.0
Reserved
0.0
Qty in PR
25
Qty in PO
8.0
In refurbishment
0
Price (USD)
$14.78
Moving average (USD)

История по SRR

Период Заказывали? Бакет Total Qty Price USD Moving avg Total Value USD
August 2026 · текущий — Нет не заказывали 0 $14.78 $10.78 $0.00
July 2026 — Нет не заказывали 0 $14.78 $10.78 $0.00
June 2026 — Нет не заказывали 0 $14.78 $21.38 $0.00
May 2026 — Нет не заказывали 0 $26.85 $21.38 $0.00
April 2026 — Нет не заказывали 0 $9.29 $11.62 $0.00
March 2026 — Нет не заказывали 0 $9.29 $11.62 $0.00
Красным — цена расходится с moving average в 5+ раз (возможная ошибка в PO/выгрузке).

Specs & sourcing

Discipline (snapshot)
ELECTRICAL
Line Type
General Line
Criticality
3.0
ABC indicator
C
Class
GLAND_CABLE · GLAND,CABLE
MRP Area / Type / Lot
1000_PGTH · VB · HB
Primary vendor
2000199 R and M ELECTRICAL GROUP LI
Manufacturer
CMP PRODUCTS LIMITED · CMP
Last PO
25/0729 · 5003458 SIGMA SOLUTIONS LLP · 8.0 × 14.78 USD

Contracts (FWAs) — 1

GLOBAL PROCUREMENT LLP
ESPE
unclaimed

Comments from latest SRR

Calculation: Rule 1

Comment: Order Qty as per MinMax Level Only. Reffer To MDEV List

MRP Controller comments — persists across SRR cycles · owned by ESPE

Select an MRP Controller in the top-right to add comments.
No comments yet. Comments added here will appear on this material in every future SRR cycle.
🔧 Work Orders 4 active reservations from last SRR snapshot Storage: PUN2 PUN3
Order Prio Storage Target finish Status Criteria T/O/S Qty
201240709 3 PUN2 2026-06-16 APPR Criteria 5 T:Y O:N S:Y 50.0
100120822 4 PUN3 2026-01-08 APPR Criteria 8 T:N O:N S:N 7.0
100120823 4 PUN3 2026-01-08 APPR Criteria 8 T:N O:N S:N 30.0
100120824 4 PUN3 2026-01-08 APPR Criteria 8 T:N O:N S:N 5.0